Connecting Channel Dredging Work in Tebet Targeted to Finish This Month

Connecting channel dredging work which carried out since January 4 on Jalan Tebet Timur Dalam XI, Tebet Timur Urban Village, South Jakarta was targeted to finish in the end of this February.

We dredge the channel to normalize the water flow

Tebet Sub-district Water Resources (SDA) Unit Head, Fachri conveyed, from total 250 meters, it has been dredged as long as 190 meters. This dredging was carried out by 6 SDA Unit personnel who dredge the channel every day using hoes, shovels, crowbars, and dustpan.

"We dredge the channel to normalize the water flow, because the mud is thick," he said, Saturday (2/13).

City Affirms River Normalization is Still Implemented as a Part of Flood Control

This channel has width about 2 meters with mud as thick as 60 centimeters thus the channel's capacity is reduced and feared to cause inundation.

"If the weather is good, we can finish the dredging in the end of February," he asserted.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1219 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1056 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye910 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye736 personFolmer
  5. TMII Prepares Stuntman Show to Music Concert

    access_time23-12-2024 remove_red_eye693 personNurito